The AACE-PSP certification is designed to help professionals stand out in a crowded job market. It demonstrates their proficiency and expertise in project management and provides credibility to their skills and knowledge. Planning & Scheduling Professional (PSP) Exam certification is particularly valuable for those working in industries such as construction, engineering, and manufacturing, where project planning and scheduling are critical to success.
NEW QUESTION # 53
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
- A. 15 days.
- B. 5 days.
- C. 10 days.
- D. 0 days.
Answer: B
NEW QUESTION # 54
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
- A. 3.9% (1 : 25.708)
- B. 9.1% (1 : 11.000).
- C. 8.6% (1 : 11.591)
- D. 2.3% (1 : 43.501).
Answer: D
NEW QUESTION # 55
What is the remaining work duration of Active D?
- A. 0
- B. 4.
- C. 3.
- D. 8.
Answer: B
NEW QUESTION # 56
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:
- A. Predecessor is activity 5001, successor is activity 8001
- B. Predecessor is activity 9001, successor is activity 9002
- C. Predecessor is activity 4001, successor is activity 8001
- D. Predecessor is activity 5001, successor is activity 8002
Answer: A
NEW QUESTION # 57
Each of the following accurately describes total float in a schedule EXCEPT:
- A. The amount of time an activity can be delayed without delaying the overall project completion time.
- B. Can be positive or negative.
- C. Computed for an activity by subtracting its early finish from its late finish, or its early start from its late start.
- D. The amount of time an activity can be delayed without delaying the start or occurrence of any other activity or event in the network.
Answer: D
NEW QUESTION # 58
Determine the correct formula and date for the late finish for Activity 2002.
- A. LS.2003 - 1 day -> 11.06.01.
- B. LS.2003 - 1 day -> 10-05-01.
- C. LS.2003 + 1 day -> 10-07-01.
- D. LS.2003 - 1 day -> 10-06-01.
Answer: B
NEW QUESTION # 59
Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?
- A. Minimizing the indirect expenditure chargeable to the contractor
- B. Avoiding a late delivery penalty from the owner
- C. Maximizing the $500,000 bonus
- D. Avoiding the 2023-2024 winter/wet weather season
Answer: B
NEW QUESTION # 60
Which of the following phases does NOT describe the commonly accepted construction life cycle?
- A. Claims and disputes phase.
- B. Turnover and start-up phase.
- C. Installation phase.
- D. Planning and design phase.
Answer: A
NEW QUESTION # 61
Which of the following is NOT a tool or technique used to perform scope planning?
- A. Benefit cost analysis.
- B. Expert Judgment.
- C. Alternatives identification.
- D. Schedule performance indexing.
Answer: D
NEW QUESTION # 62
In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:
- A. on schedule
- B. behind schedule
- C. ahead of schedule
- D. complete
Answer: C
NEW QUESTION # 63
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
- A. Direct or indirect cost.
- B. Labor hours or dollars.
- C. Linear feet or dollars.
- D. Earned or budgeted cost yearly.
Answer: D
NEW QUESTION # 64
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity 2002?
- A. 08 Sep 2021
- B. 09 Sep 2021
- C. 27 Aug 2021
- D. 19 Sep 2021
Answer: D
NEW QUESTION # 65
Determine the correct formula and date for the late finish for Activity 9004.
- A. LS of 9004 plus 72 days
- B. LF of 10002 less 24 days
- C. LF of 8001 plus 72 days
- D. LS of 10002 less lag of 7 days plus 1 day equaling 20 Nov 2023
Answer: B
NEW QUESTION # 66
Which activity is drawn in the incorrect position?
- A. Activity D.
- B. Activity E.
- C. Activity C.
- D. Activity G.
Answer: A
NEW QUESTION # 67
How many work days does it take to move the product from testing to sale?
- A. 100.
- B. 90.
- C. 70.
- D. 60.
Answer: A
NEW QUESTION # 68
What is the free float for Activity F?
- A. 0months.
- B. 1months.
- C. 2month.
- D. 3 months.
Answer: A
NEW QUESTION # 69
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.
PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the
"normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.
Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?
- A. $524,000.
- B. $420,000.
- C. $552,000.
- D. $307,000.
Answer: C
NEW QUESTION # 70
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?
- A. Non-excusable delay
- B. Compensable delay
- C. Excusable delay
- D. Non-compensable delay
Answer: A
NEW QUESTION # 71
In a graphical earned value analysis, what time-scaled value determines the reporting intervals for both schedule and cost performance?
- A. Budgeted cost of work scheduled
- B. Schedule performance index
- C. Budgeted cost of work performed
- D. Actual cost of work scheduled
Answer: A
NEW QUESTION # 72
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.
- A. The government's report on future high-clearance bridge projects
- B. The project geotechnical report
- C. The regulations published by the government aviation agency
- D. The project plans and specifications
Answer: A
NEW QUESTION # 73
If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?
- A. 0 calendar days.
- B. 10 calendar days.
- C. -20 calendar days.
- D. -14 calendar days.
Answer: D
NEW QUESTION # 74
Time-scaled logic diagrams are
- A. Used to calculate the most probable activity duration.
- B. The same as a pure-logic diagram.
- C. Only calculated using a computer.
- D. Logic networks that are drawn to match the calendar.
Answer: A
NEW QUESTION # 75
......
The AACE-PSP Exam consists of 120 multiple-choice questions that cover a range of topics related to project planning and scheduling. These topics include project scheduling concepts, time management techniques, critical path method (CPM) analysis, and earned value management (EVM). AACE-PSP exam also covers risk management concepts, including risk identification, analysis, and mitigation. Candidates must complete the exam within four hours and achieve a passing score of 70% or higher to earn the AACE-PSP certification.
Check your preparation for AACE International AACE-PSP On-Demand Exam: https://www.itcertmagic.com/AACE-International/real-AACE-PSP-exam-prep-dumps.html
Practice Exam AACE-PSP Realistic Dumps Verified Questions: https://drive.google.com/open?id=1YO8aqh64BZdsBBbVeTeI9VGd8dsIsy80