SAP C_TS412_1909 Exam Description:
The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.
SAP C_TS412_1909 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Cost and Budgets > 12% | Describe procedures for establishing budgets and reporting costs. |
| Project Structures > 12% | Name the components of Work Breakdown Structure, Network and activities, Milestones |
| Material > 12% | Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement |
| Dates > 12% | Describe the importance of various dates which can be tracked for projects |
| Revenues and Payments > 12% | Describe the characteristics of Revenues & Payments. |
| Resources > 12% | Describe how the Resource Planning process integrates with HCM |
| Reporting < 8% | Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports |
C_TS412_1909 Exam Certification Details:
| Languages: | English |
| Duration: | 180 mins |
| Exam: | 80 questions |
| Cut Score: | 51% |
| Sample Questions: | SAP C_TS412_1909 Exam Sample Question |
| Level: | Associate |
NEW QUESTION 10
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
- A. The MRP controller for the network
- B. The person responsible for the work center
- C. The person responsible for the network activity
- D. The person responsible for the superior WBS element
Answer: A
NEW QUESTION 11
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?
- A. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
- B. Set up the requirement date manually as February 5.
- C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
- D. Set up the requirement date aligned with the activity start date and an offset of 5 days.
Answer: D
NEW QUESTION 12
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.
- A. Cost element reports
- B. Hierarchical reports
- C. Resource reports
- D. Structure information system reports
Answer: D
NEW QUESTION 13
You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?
- A. Unit costing for WBS
- B. Planning of overall values
- C. Detailed planning for WBS
- D. Easy Cost Planning (ECP) for WBS
Answer: B
NEW QUESTION 14
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are
3 correct Answers to this question.
- A. Generate delivery
- B. Generate purchase requisition
- C. Stock transfer posting
- D. Confirm production order
- E. Cancel goods issue
Answer: A,B,C
NEW QUESTION 15
Where do you control whether a project stock is managed as valuated or non-valuated project stock?
- A. In the project definition
- B. In the network activity
- C. In the WBS element
- D. In the material master
Answer: A
NEW QUESTION 16
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
- A. Basic dates of the network activity
- B. Basic dates of the WBS
- C. Forecast dates of the WBS
- D. Actual dates of the network activity
Answer: A
NEW QUESTION 17
What functionality can you perform with activity elements?
- A. Assign material
- B. Assign work centers and capacities
- C. Schedule WBS elements
- D. Create relationships
Answer: D
NEW QUESTION 18
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
- A. The material master is set to external procurement.
- B. The material is assigned to the activity as a non-stock material.
- C. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
- D. The availability check for material components indicates missing parts.
Answer: C,D
NEW QUESTION 19
Which object is used to allocate the costs from a claim to the project structure?
- A. Network activity
- B. Internal order
- C. Claim
- D. WBS element
Answer: B
NEW QUESTION 20
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.
- A. An MRP group must be assigned.
- B. The exact lot size procedure must be used.
- C. The procurement type of the material must be internal.
- D. The materials must allow sales order or project stock.
Answer: A,D
NEW QUESTION 21
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
- A. The table of MRP controllers
- B. The control key
- C. The network profile
- D. The scheduling parameters for the network
Answer: D
NEW QUESTION 22
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing material availability
- B. Missing authorizations to release material components
- C. Missing reservations for material components
- D. Missing budget for material components
Answer: B
NEW QUESTION 23
Which objects can be used to specify settlement rules? Note: There are 2 correct Answers to this question.
- A. Network activity for activity-account-assigned networks
- B. Network header for activity-account-assigned networks
- C. Standard WBS elements
- D. WBS elements
Answer: B,D
NEW QUESTION 24
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
- A. Third-party order
- B. Purchase requisition and Reservation for WBS element
- C. Preliminary purchase requisition for WBS element
- D. Planned order
- E. Reservation for WBS element
Answer: B,C,E