Achieve the PRINCE2Foundation Exam Best Results with Help from PRINCE2 Certified Experts [Q265-Q283]

Share

Achieve the PRINCE2Foundation Exam Best Results with Help from PRINCE2 Certified Experts

Provide PRINCE2Foundation Practice Test Engine for Preparation


The EXIN PR2F (PRINCE2 Foundation written) Exam is an internationally recognized certification exam that is designed to test an individual's knowledge of the PRINCE2 project management methodology. PRINCE2 (Projects IN Controlled Environments) is a widely adopted project management framework that is used by organizations across various industries to manage their projects efficiently and effectively. The PR2F exam is an entry-level certification exam that is a prerequisite for individuals who want to pursue higher-level PRINCE2 certifications.

 

NEW QUESTION # 265
What must be done for a project to be a PRINCE2 project?

  • A. The project must meet the minimum requirements for applying the themes
  • B. The project must form part of a programme or portfolio
  • C. The project roles must be combined wherever possible
  • D. The project must use the recommended approach to planning

Answer: A

Explanation:
For a project to be considered a PRINCE2 project, it must meet the minimum requirements for applying the seven PRINCE2 themes. These themes (Business Case, Organization, Quality, Plans, Risk, Change, and Progress) provide a framework for managing the project and ensuring that it is conducted in a systematic, consistent manner that is aligned with PRINCE2 principles.References: = PRINCE2 7 Foundation handbook and online resources


NEW QUESTION # 266
Which product identifies the management stages and timescales of a project?

  • A. Project Product Description
  • B. Project Plan
  • C. Project Brief
  • D. Initiation Stage Plan

Answer: B


NEW QUESTION # 267
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

  • A. Stage Plan
  • B. Project Plan
  • C. Team Plan
  • D. Benefits Review Plan

Answer: A


NEW QUESTION # 268
Why is the 'learn from experience' principle applied to a project?

  • A. To allow the project to be divided into management stages
  • B. To enable the project team to repeat successes from previous projects
  • C. To enable the project team to use tolerances to delegate authority
  • D. To enable the project team to develop a business case for the project

Answer: B

Explanation:
Explanation/Reference:
Reference https://link.springer.com/chapter/10.1007/978-3-319-23000-9_4


NEW QUESTION # 269
Why does PRINCE2 recommend three different levels of plans?

  • A. To provide appropriate detail to each of the different levels of management within the project
  • B. To match the different aspects of the product-based planning technique
  • C. To cover initiation, specialist work and exception situations
  • D. As an allowance for initiation, product delivery and project closure

Answer: A


NEW QUESTION # 270
Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?

  • A. Creating a product flow diagram
  • B. Documenting the plan
  • C. Writing the product description
  • D. Writing a project product description

Answer: A

Explanation:
Section: Volume B


NEW QUESTION # 271
What is being addressed when the project manager plans to keep the CO2 emissions of the project aligned with the business strategy?

  • A. Delivery sustainability
  • B. Sustainability risk
  • C. Benefits sustainability
  • D. Product sustainability

Answer: A


NEW QUESTION # 272
Which statement about time-driven controls is CORRECT?

  • A. An exception report is a time-driven control
  • B. Time-driven controls are produced at the end of a stage
  • C. Time-driven controls are used for monitoring the progress of work packages and management stages
  • D. Time-driven controls take place when specific events happen

Answer: C

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Progress#Event-Driven_and_Time-Driven_Controls


NEW QUESTION # 273
Which is a definition of management?

  • A. Assigning people with specific skills and capabilities to work on multiple projects
  • B. Instructing the execution of tasks in line with agreed ways of working
  • C. Translating stakeholder requirements into quality criteria
  • D. Defining, assuring, and accepting products back into the business

Answer: B

Explanation:
The definition of management within the context of PRINCE2 relates to instructing the execution of tasks according to predefined, agreed-upon methods or standards. This encapsulates the directive aspects of management, ensuring tasks are completed as planned and in alignment with the project's goals and processes.References: PRINCE2 7 Foundation handbook and guide on management principles.


NEW QUESTION # 274
Which is a minimum requirement for applying the organization theme?

  • A. The frequency of communication to the project's stakeholders must be documented
  • B. The roles of the project management team must be combined, wherever possible
  • C. The project manager must be appointed from the supplier organization
  • D. Each member of the project management team must have a written role description

Answer: D

Explanation:
According to the PRINCE2 methodology, a key requirement for applying the organization theme is ensuring that each member of the project management team has a clear and written role description. This document outlines their duties, responsibilities, and relationships to other roles within the project, which is fundamental for organizational clarity and accountability. References: PRINCE2 7 Foundation Handbook and official training materials.


NEW QUESTION # 275
Which is a true statement about time-driven controls?

  • A. Time-driven controls are produced at the end of a stage
  • B. Time-driven controls are used for monitoring the progress of Work Packages and management stages
  • C. An Exception Report is a time-driven control
  • D. Time-driven controls take place when specific events happen

Answer: B

Explanation:
Time-driven controls in PRINCE2 are specifically designed to monitor the progress of Work Packages and management stages at regular intervals. These controls ensure that the project stays on schedule and that any deviations are identified and managed promptly. References: PRINCE2 Foundation official study materials.


NEW QUESTION # 276
Which is a minimum requirement for applying the risk theme?

  • A. Team managers must maintain their own risk registers
  • B. The PRINCE2 risk management procedure must be followed
  • C. Threats must be assessed for their impact on the viability of the project
  • D. A single role that is responsible for all risks must be defined

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-2017-risk-theme-changes/


NEW QUESTION # 277
Who carries out audits that are independent of the project?

  • A. Project Assurance
  • B. Project Manager
  • C. Project Support
  • D. Quality assurance

Answer: D


NEW QUESTION # 278
The project manager reviews the project product description to identify the detailed requirement for each product.
In which step of the quality management technique should the project manager do this review?

  • A. Describing the quality management approach
  • B. Gathering user inputs
  • C. Accepting products ay
  • D. Controlling quality

Answer: B

Explanation:
Reviewing the project product description to identify detailed requirements for each product aligns with the step of 'Describing the Quality Management Approach' in the quality management technique. This step involves defining how quality will be managed and controlled throughout the project, ensuring that all product requirements are understood and planned for in accordance with the project's quality expectations.References:
PRINCE27 Foundation guide on quality management.


NEW QUESTION # 279
Which is a difference between management and technical stages?

  • A. Technical stages require resources and management stages do not
  • B. Management stages require planning and technical stages do not
  • C. Management stages deliver products and technical stages do not
  • D. Technical stages can overlap and management stages cannot

Answer: D


NEW QUESTION # 280
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?

  • A. Off-specifications
  • B. Follow-on action recommendations
  • C. Issue Register
  • D. Risk Register

Answer: B

Explanation:
Follow-on action recommendations are used to document any uncompleted work or additional actions required after the project closure. These recommendations ensure that any outstanding issues or incomplete deliverables are addressed, even after the project has officially closed. References: PRINCE2 Foundation official study guide and materials.
These responses are crafted based on the official PRINCE2 guidelines and documentation, ensuring that they are reflective of the most current practices within the PRINCE2 methodology.


NEW QUESTION # 281
Identify the missing words in the following sentence.
The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

  • A. change, quality, risk,
  • B. benefits, quality, risk,
  • C. benefits, change, risk,
  • D. benefits, change, quality,

Answer: B

Explanation:
The six aspects of project performance to be managed, as outlined in PRINCE2, are benefits, costs, timescales, scope, quality, and risk. Managing these aspects helps ensure that the project delivers its intended outputs while adhering to predetermined constraints and achieving desired outcomes.
= PRINCE2 7 Foundation handbook and online resources


NEW QUESTION # 282
Which describes risk probability?

  • A. Level of risks which the project can tolerate before escalating to the Project Board
  • B. Timeframe within which the risk may occur
  • C. A measure of the likelihood of the risk occurring
  • D. Probable effect on the project delivering its objectives

Answer: C


NEW QUESTION # 283
......


PRINCE2 Foundation certification exam is a multiple-choice exam that consists of 60 questions. Candidates have 60 minutes to complete the exam, and they must achieve a score of 55% or higher to pass. PRINCE2Foundation exam tests candidates’ understanding of the PRINCE2 methodology, including the seven principles, seven themes, and seven processes. PRINCE2Foundation exam is designed to test candidates’ knowledge of the PRINCE2 methodology and their ability to apply it in real-world project management scenarios.


The EXIN PR2F (PRINCE2 Foundation written) Certification Exam is a globally recognized qualification that validates a professional’s understanding of the PRINCE2 (Projects IN Controlled Environments) methodology. PRINCE2 7 Foundation written Exam certification is an entry-level qualification that teaches the fundamental principles, concepts, and terminology of PRINCE2 to professionals working in project management or those interested in pursuing a career in project management. PRINCE2 7 Foundation written Exam certification exam is designed to assess a candidate’s understanding of the PRINCE2 methodology and their ability to apply it in real-life scenarios.

 