NEW QUESTION # 29
Which statement about timeboxes is CORRECT?

  • A. A timebox can contain another timebox
  • B. Flow based working partitions work into timeboxes
  • C. Timeboxes should be avoided in business as usual environments
  • D. A project cannot be referred to as a timebox

Answer: A


NEW QUESTION # 30
Which statement about the waterfall methodology definition is CORRECT?

  • A. It has distinct goals for each stage of development
  • B. It states that deadlines should not be moved
  • C. It promotes the use of experiments carried out in a scientific way
  • D. It is a behavior that involves making things transparent

Answer: A


NEW QUESTION # 31
Which describes the Scrum Master role in Scrum?

  • A. It is empowered to organize and manage its own work to create a valuable, useful increment every sprint
  • B. It is responsible for ensuring that product backlog items are clearly expressed on the product backlog
  • C. It is servant-leadership to help everyone change their interactions to maximize the value created by the team
  • D. It is authorized to run the project on a day-to-day basis on behalf of the project board

Answer: B


NEW QUESTION # 32
Which TWO project board responsibilities are specifically assigned to the senior user?
1) Demonstrating the achievement of benefits.
2) Specifying the needs of those impacted by the outputs.
3) Balancing business, user and supplier demands.
4) Ensuring that the project delivers value for money.

  • A. 1 and 4
  • B. 2 and 3
  • C. 1 and 2
  • D. 3 and 4

Answer: C


NEW QUESTION # 33
What BEST defines embryonic customer requirements?

  • A. Technical stories
  • B. Sub-products
  • C. 'Fine-grained' user stories
  • D. Epics

Answer: D


NEW QUESTION # 34
Which is a key objective of running a workshop?

  • A. To encourage collaboration and create the defined outputs from the event
  • B. To make day-to-day decisions on behalf of the delivery team within a sprint
  • C. To communicate decisions to the wider stakeholder community
  • D. To make daily progress visible to the delivery team and key stakeholders

Answer: A


NEW QUESTION # 35
What term is used to describe boards that display what work needs to be completed for people working on a project?

  • A. Highlight report
  • B. Glad! Sad! Mad!
  • C. Work in progress limit
  • D. Information radiator

Answer: A


NEW QUESTION # 36
Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should attend regular project progress meetings
  • B. A project board member should fulfill the product owner role within a delivery team
  • C. The project board should make decisions based on the Agilometer risks
  • D. The project board should increase the stage-level time tolerance

Answer: B


NEW QUESTION # 37
When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?

  • A. It should be used when planning at the delivery level
  • B. It should be used when monitoring the amount of products delivered
  • C. It should be used when planning at the project level
  • D. It should be used when controlling the quality of the products delivered

Answer: C


NEW QUESTION # 38
Which is an advantage of using the PRINCE2 Agile behavior 'collaboration'?

  • A. It uses experimentation to expand requirements
  • B. It uses learning to help improve products
  • C. It ensures that there are no surprises
  • D. It allows people to provide cover for one another

Answer: B


NEW QUESTION # 39
Which is a benefit of the Lean Startup approach to releasing a product?

  • A. It enables the release plans to be synchronized with the PRINCE2 plans
  • B. It provide a technique to reduce the testing of a product before release
  • C. It reduces the number of people needed to manage a release of a product
  • D. It provides quick feedback that can be responded to at the earliest opportunity

Answer: A


NEW QUESTION # 40
Which is the BEST method of communication to gather feedback?

  • A. Meeting face-to-face to encourage an exchange of views
  • B. Conducting online surveys to obtain a range of opinions
  • C. Discussing over the telephone to gather feedback quickly from stakeholders
  • D. Receiving emailed diagrams to encourage discussion

Answer: A


NEW QUESTION # 41
Which well-known agile method uses visualization, and controls work in progress?

  • A. Scrum
  • B. Lean Startup
  • C. Kanban
  • D. Lean

Answer: C


NEW QUESTION # 42
Which statement about the 'accept that the customer doesn't need everything' target is CORRECT?

  • A. It is based on the concept that people generally use a limited number of product features
  • B. It enables a more accurate final product to be produced
  • C. It is achieved by ensuring that the operational product has complete documentation
  • D. It is achieved by testing only a few features to deliver on time

Answer: A


NEW QUESTION # 43
Which statement about the PRINCE2 Agile behaviour 'collaboration' is CORRECT?

  • A. It allows many small learnings to accumulate over time
  • B. It uses the most effective channel to communicate
  • C. It allows the delivery team to decide how best to get the job done
  • D. It creates a shared ownership of goals

Answer: D


NEW QUESTION # 44
......